Quartzite Installation Access Survey: Doorways & Lifts

A quartzite installation access survey should be completed before oversized countertops, islands, wall panels or other difficult pieces are released for cutting. The survey should follow the real delivery route from unloading to the final installation position and record clear doorway openings, lift dimensions and capacity, corridor widths, turning zones, height restrictions, temporary staging areas and the handling equipment that can actually be used. If the route cannot accommodate the proposed finished piece safely, the solution should be resolved in the fabrication layout before the stone is cut. Quick SummaryA drawing can prove that a quartzite island fits in the room without proving that the finished island can reach the […]